  • Positioning of the columns:
    once markings have been made and finished levels checked, the first operation to be carried out when laying a raised floor is to position the columns following the set points on the traced modular grid.


  • Positioning of the cross-section stringers:
    the columns are then joined together using cross-section stringers, which are screwed, bolted of fitted with fixed joints to the ends of the columns.


  • Positioning of the gaskets on the cross-section stringers:
    PVC gaskets are fitted onto the cross-section stringers to give the panels better support.


  • Levelling:
    now the structure is ready to be levelled according to the heights of the finished floor on the site.


  • Positioning of the panel:
    the panels are laid on the assembled structure and checked at each apex to make sure that they are correctly resting on the structure.


  • Completion of the flooring:
    after the edges have been cut and a final check has been carried out, the floor is completed.


Welcome to Granitech

Granitech deals with design and installation of ventilated walls and raised floors. Using state-of-the art technologies Granitech develops top quality solutions for important projects in contemporary architecture.

Ventilated Facades

Ventilated walls are multi-layer construction solutions for "dry" cladding of outside walls, improving their aesthetic qualities, degree of protection and insulation.

Read more

Floating Floors

A raised floor is a flooring systems designed to meet the different needs of working areas with high concentration of plant engineering systems.

Read more